Sydney Metro Expansion: Next Phases Lock in Tunnel and Upgrade Timelines
With the initial metro phase in operation, focus shifts to remaining segments, tunnel connections and fast-tracked upgrades.
Listen in English · 3 min
How we reported this

The first phase of Sydney Metro City & Southwest opened on 19 August 2024, introducing driverless trains through the CBD and harbour between Chatswood and Sydenham.
Metro Completion Path
The remaining Bankstown line segment from Sydenham to Bankstown is scheduled to open in 2026. This step will finish the full 30.5 km metro rail project and extend direct services along the southern corridor.
Western Harbour Tunnel Outlook
The $74 billion Western Harbour Tunnel is anticipated to open in late 2028. It will connect WestConnex to the northern suburbs and provide a route that bypasses the CBD, altering cross-harbour travel patterns once operational.
Metro West Revision
Metro West is revised to open in 2032 with a potential cost of up to $29 billion. The project will link the CBD to western Sydney once delivered.
Fast-Track Infrastructure Spend
NSW invested $40.9 million to fast-track critical infrastructure. This covers road upgrades in Waterloo and a pedestrian link through Parramatta CBD, with delivery expected by mid-2026.
Key Decisions Ahead
Project teams will now coordinate integration of the 2026 metro segment with existing services, manage construction sequencing for the 2028 tunnel, and align the 2032 western extension with broader network planning. Delivery of the $40.9 million upgrades by mid-2026 will also require ongoing oversight of the Waterloo and Parramatta works.
Residents and businesses can monitor official project updates through the listed government infrastructure sites for any schedule adjustments or public consultation opportunities.
{"sources":[{"url":"https://www.infrastructure.nsw.gov.au/industry/construction-industry/pipeline-of-projects/","title":"Sydney Metro City & Southwest first phase details"},{"url":"https://section94.com.au/sydneys-biggest-infrastructure-projects/","title":"Bankstown line segment schedule"},{"url":"https://www.budget.nsw.gov.au/sites/default/files/2025-06/bp3-infrastructure-statement-chapter3-key-infrastructure-developments-delivered-across-new-south-wales-nsw-budget-2025-26.pdf","title":"Western Harbour Tunnel cost and timeline"},{"url":"https://ppp.worldbank.org/library/project-evaluation-summary-sydney-metro-city-and-southwest","title":"Metro West revised opening and cost"},{"url":"https://www.infrastructureaustralia.gov.au/sites/default/files/2019-06/Sydney_Metro_City_Southwest_Summary.pdf","title":"NSW $40.9 million fast-track investment"}]}References Sourced but Not Limited to:
- ppp.worldbank.org · Project evaluation summary sydney metro city and southwest
- infrastructureaustralia.gov.au · Sydney Metro City Southwest Summary
- en.wikipedia.org · Sydney Metro City & Southwest
- planning.nsw.gov.au · Nsw government investing 409 million fast track critical infrastructure...
- infrastructure.nsw.gov.au · Projects nsw
- infrastructure.nsw.gov.au · Pipeline of projects